A.17 Gill Creek, NY
A.17.1 Summary
|
Environment: |
Freshwater |
|
Scale: |
Field |
|
Contaminants of Concern: |
VOCs, Mercury, PCBs: 11,000 ppm |
|
Final Remedy: |
Hydraulic and mechanical dredging using cofferdams and sandbags for to dewatering. Sediment was stabilized with fly ash and kiln dust then transported to an RCRA and TSCA permitted landfill. 230 yd3 was deemed hazardous and was incinerated. |
A.17.2 Site Description
The site is owned by E.I. DuPont and consists of a 250-foot sector of creek near its confluence with the Niagara River.
Year: 1992
Target Volume:
- Area 1: 3,400 yd3
- Area 2: 160 yd3
- Area 3: 40 yd3
Actual Volume Removed: 8,020 yd3
A.17.3 Remedial Objectives
- BHCs: 0.045 ppm
- PAHs: 22 ppm
- Mercury: 0.2 ppm
A.17.4 Remedial Approach
Only sites OU 3–OU 5 were dredged. A compacted clay liner was installed to prevent groundwater seepage into creek.
A.17.5 Monitoring
Contaminant concentrations were significantly lower after dredging. No cappingTechnology which covers contaminated sediment with material to isolate the contaminants from the surrounding environment. was required for this site. Post-remediationThe act or process of abating, cleaning up, containing, or removing a substance (usually hazardous or infectious) from an environment. monitoring was planned for 5 years, consisting of sediment and water sampling.
RAOs/project objectives achieved? Based on confirmatory sampling, cleanup levels were met. A long term monitoring plan is in place to assure the protection of human health and the environment.
A.17.6 References
U.S. EPA. Realizing Remediation II An Upland Summary of Contaminated Sediment Remediation Activities at Great Lakes. July 2000. http://www.epa.gov/glnpo/sediment/realizing2/RR2report.PDF.
Major Contaminated Sediment Sites Database; Sept. 2004 as updated 2008. http://www.smwg.org/MCSS_Database/MCSS_Database_Docs.html.
Publication Date: August 2014